Exciting Progress on the first Pier as New Pontoon Sections Arrive Daily
Construction of the first 44-berth pier, M-Pier, is creating a buzz. Daily arrivals of new pontoon sections signal progress. With Total...
-
Jul 221 min read


Reclamation completed to settlement level above high tide.
New marina in Whangarei ready for stage 2.
-
Nov 28, 20241 min read


Taking shape with the land reclamation in full swing
On site now is 1 tug, 2 dredging barges, 1 piling barge, 4 trucks, 2 diggers, and 1 pile-driving crane. The construction process involves...
-
Feb 24, 20241 min read


Construction Launch
Construction kick-off was celebrated together with Contractors, Neighboring businesses, Berth holders, Whangarei's Mayor, Staff and the...
-
Aug 31, 20231 min read